Kavango Resources has achieved statutory commissioning of its 50 tonne per day (tpd) gold processing plant and tailings storage facility (TSF) at the Hillside Gold Project in Zimbabwe.
The Ministry of Mines & Mining Development permitted the commissioning on 30 October 2026.
The plant processes ore through crushing, milling, gravity concentration, and a carbon-in-leach (CIL) circuit.
During commissioning, gold production increased from 397g at the first elution in August to 539g in September.
The Bill's Luck Underground hosts a JORC Mineral Resource of 33,900 ounces of gold at 2.68 grammes per tonne (g/t), with expected plant recoveries of 90-93%.
The pilot plant serves as a proof-of-concept facility to optimise processing performance and confirm metallurgical recoveries, providing data to support the design and installation of a larger commercial-scale plant.
"Achieving statutory commissioning of the processing plant and TSF is a significant milestone for Hillside and an important step towards commercial-scale operations," said Kavango chief executive Jasper Musadaidzwa.
Alongside commissioning, the company is upgrading site infrastructure to support future growth.
This includes installing a 13-metre headframe at Bill's Luck Main Vertical Shaft, upgrading power and water supply infrastructure, planning future exploration programmes, and developing an enhanced employee accommodation camp.
Mathew Nyaungwa, Editor-in-Chief, Rough & Polished