De Beers shines light on budding jewellery designers

Diamond giant De Beers will this year conduct its bi-annual Shining Light Awards jewellery design competition. De Beers beneficiation manager Kagiso Fredericks told Rough & Polished's Mathew Nyaungwa in an exclusive interview they set aside 4.5 carats...

22 july 2024

DiaMondaine Diamantaires Club mulls diamond safari tours in southern Africa

DiaMondaine Diamantaires Club (DDC) is set to organise diamond safari tours in southern Africa, home to major diamond-producing countries. DDC founder Agnes Abdulahu told Rough&Polished’s Mathew Nyaungwa that the launch of the first diamond safari...

15 july 2024

Vladislav Zhdanov: Questions of efficiency and investment potential of diamond mining versus diamond growing pique keen interest

Vladislav Zhdanov is Professor at the National Research University Higher School of Economics (HSE). He told Rough&Polished about new researches into the effectiveness of diamond production methods.

02 july 2024

Why it's expensive to cut and polish diamonds in Africa? ADMA president António Oliveira has the answer

The African Diamond Manufacturers Association (ADMA) president António Oliveira told Rough&Polished’s Mathew Nyaungwa in an exclusive interview that the lack of a robust infrastructure in Africa fails to accelerate and encourage manufacturing...

24 june 2024

Edahn Golan: IPO feasible but not Anglo’s preferred way to sell De Beers

Edahn Golan, owner of the eponymous Edahn Golan Diamond Research and Data, told Rough&Polished's Mathew Nyaungwa in an exclusive interview that while an IPO of De Beers is “feasible,"  he does not think this is a route Anglo American...

17 june 2024

Lucara underground expansion project will take longer, and cost more money

19 july 2023

Lucara Diamond’s underground expansion project (UGP) at the Karowe mine in Botswana has been delayed by a year and a half, and the capital cost to complete it has gone up by $136 million.

The UGP, which seeks to extend mine life to at least 2040, will now only be finished by the first half of 2028 rather than the originally projected date of the second half of 2026.

As a result, estimated expenditures to finish the project rose by 25% to $683 million from the May 2022 estimated capital cost of $547 million.

Lucara said capital expenditures of $264.5 million had been incurred and capital commitments of $369.7 million had been made as of June 30, 2023.

“Schedule delays due to longer than anticipated grouting activity have impacted the project timeline, however, the grouting methodology selected has proven to be effective in controlling water inflows,” said company chief executive Eira Thomas.

“As we transition out of the sandstones early in the fourth quarter of 2023, we look forward to meeting planned sinking rates.”

Grouting programmes took longer than expected due to a combination of high-water volumes in the sandstone lithologies between 870 and 752 metres above sea level in depth (144 metres to 262 metres below the shaft collar) combined with technical challenges associated with the transition to main sinking.

Mathew Nyaungwa, Editor in Chief of the African Bureau, Rough&Polished