Dr M'zée Fula Ngenge: Demand for considerable-sized diamonds stronger than ever

The African Diamond Council (ADC) chairperson Dr M'zée Fula Ngenge told Rough & Polished’s Mathew Nyaungwa in an exclusive interview that although overall global diamond prices have been somewhat soft, the demand for considerable-sized diamonds...

02 september 2024

Amplats sees prospects as a standalone company

Anglo has revealed its plans to demerge Anglo American Platinum (Amplats), which has operations in South Africa and Zimbabwe, to optimise shareholder value. Rough&Polished contacted Amplats to comment on this and other issues but was referred...

19 august 2024

WFDB President Yoram Dvash Remains Confident Despite Global Diamond Challenges

Yoram Dvash is President of the World Federation of Diamond Bourses (WFDB) having been elected in 2020. He found time in his busy schedule to speak to Rough&Polished about the state of the diamond industry around the world and some of the major...

12 august 2024

Lyudmila Vysotskaya: Amber is a mystical stone, a living substance

Lyudmila Vysotskaya is a Kaliningrad-based amber artist and designer, expert, chairwoman of the Amber Academy and member of the Creative Union of Artists in Decorative and Applied Arts. This summer, visitors could admire the art works by Lyudmila Vysotskaya...

30 july 2024

De Beers shines light on budding jewellery designers

Diamond giant De Beers will this year conduct its bi-annual Shining Light Awards jewellery design competition. De Beers beneficiation manager Kagiso Fredericks told Rough & Polished's Mathew Nyaungwa in an exclusive interview they set aside 4.5 carats...

22 july 2024

Lucara underground expansion project will take longer, and cost more money

19 july 2023

Lucara Diamond’s underground expansion project (UGP) at the Karowe mine in Botswana has been delayed by a year and a half, and the capital cost to complete it has gone up by $136 million.

The UGP, which seeks to extend mine life to at least 2040, will now only be finished by the first half of 2028 rather than the originally projected date of the second half of 2026.

As a result, estimated expenditures to finish the project rose by 25% to $683 million from the May 2022 estimated capital cost of $547 million.

Lucara said capital expenditures of $264.5 million had been incurred and capital commitments of $369.7 million had been made as of June 30, 2023.

“Schedule delays due to longer than anticipated grouting activity have impacted the project timeline, however, the grouting methodology selected has proven to be effective in controlling water inflows,” said company chief executive Eira Thomas.

“As we transition out of the sandstones early in the fourth quarter of 2023, we look forward to meeting planned sinking rates.”

Grouting programmes took longer than expected due to a combination of high-water volumes in the sandstone lithologies between 870 and 752 metres above sea level in depth (144 metres to 262 metres below the shaft collar) combined with technical challenges associated with the transition to main sinking.

Mathew Nyaungwa, Editor in Chief of the African Bureau, Rough&Polished