Aim-listed Sylvania Platinum, through its wholly owned subsidiary Sylvania Metals, has triggered the termination clause in its joint venture agreement for the Limpopo-based Thaba JV.
The company cited consistent mining underperformance since commissioning, including lower-than-planned run-of-mine ore tonnages and chrome and PGM feed grades, as well as significantly higher mining costs. Sylvania and its JV partner were unable to agree on a revised basis for the venture to continue, leading Sylvania to believe termination is the most appropriate action to protect shareholder value.
Following termination, Sylvania has an option to continue treating the tailings storage facility (TSF) on site and to enter into a Use and Access agreement with the JV partner to operate relevant sections of the processing plant.
Processing at the TSF is expected to support on-site operations for four-and-a-half years, with the operation incorporated under Sylvania Dump Operations.
Under the JV agreement, Sylvania funded the total capital expenditure and subsequent working capital from its own cash resources, including the partner's 50% share via interest-bearing loans.
The combined outstanding loans, including accrued interest, amount to about $51.1 million as at October 31.
These loans will become due and payable by the partner once the JV reaches official termination and are secured by Special Notarial Bonds over the partner's chrome TSF resource.
As a result of the termination, the board has revised its guidance for the 2027 financial year.
While PGM production guidance remains unchanged at 85,000 oz to 95,000 oz of 4E PGMs, chrome production guidance has been reduced to between 75,000 t and 85,000 t of chrome concentrate, down from the previous guidance of 110,000 t to 140,000 t.
The group's Sylvania Dump Operations are unaffected and will continue operating as normal.
Mathew Nyaungwa, Editor-in-Chief, in Luanda, Angola, Rough & Polished